PFIs and adjudication
As of 2017, the UK government's Private Finance Initiative (PFI) is now 25 years old. Introduced to change the way the public sector procures infrastructure, it has certainly achieved that aim.
PFI projects are necessarily complex in their contractual structure and the number of parties involved tends to be greater than in traditional procurement. That in turn can lead to a greater number of disputes than before and of greater complexity.
The growth in PFI activity in the 1990s and 2000s was in parallel to the developments in statutory provisions for adjudication through the HGCRA. PFI agreements are excluded from the provisions of the act through accompanying legislation, but that exclusion does not apply entirely to PFI subcontracts which are construction contracts under the act.
S.113 of the act prohibits pay-when-paid clauses which leads to an inability to fully enforce equivalent project relief provisions (ways of enforcing back-to-back risk transfer down the supply chain) by PFI project companies.
This was the situation in Midland Expressway. Project companies are typically thinly capitalised and prolonged disputes involving subcontractors and potentially the public sector authority can cause significant cash flow difficulties. Subsequent contracts legislation in 2011 eased this burden slightly but the ban on pay-when-paid remains.
These characteristics point to the usefulness of adjudication as a relatively quick form of dispute resolution in the PFI market. The joining of related disputes is a helpful feature as most disputes involve more than two parties and more than one contract.
Despite the S.113 exemption, PFI project agreements almost always contain contractual adjudication provisions for dispute resolution which tend to be closely followed by those drafting subcontracts, for example using the same panel(s) of adjudicators.
Better value from existing private finance initiatives:
The UK government's austerity measures brought in after the credit crunch led public authorities to seek better value from existing PFI agreements and this in turn has led to a significant rise in disputes under PFI contracts between authorities, project companies and subcontractors.
The factual matrix of the Portsmouth City Council highways case, while one of only a very small number to reach the courts, was typical of many other PFI projects.
Most public bodies, and probably their contractual partners, prefer to avoid the sometimes unflattering exposure brought by litigation so once again adjudication is a natural route to take given its confidentiality.
The PFI market is now mature as are many of the assets procured through its use. Lifecycle expenditure is an important consideration for project companies and their asset maintenance subcontractors.
Disputes between private sector parties about the responsibilities for asset maintenance and asset replacement are now common and are now being seen frequently in adjudications. Also common at present are disputes brought by public authorities for building defects.
The long-term nature of PFI agreements (typically at least 25 years), means that the market isn't going to disappear despite the slowness of government to develop replacement models for PFI-style projects. Whether the current propensity to disputes will continue, only time will tell.
This article was originally published here on 8 March 2017 by ICE. It was written by Patrick Waterhouse - a construction adjudicator and is on ICE's panel of adjudicators and panel of conciliators/mediators.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
- Articles by ICE on Designing Buildings Wiki.
- Adjudication.
- Adjudicators and bias.
- Causes of construction disputes.
- Concession agreement.
- Equivalent project relief provisions.
- Housing Grants, Construction and Regeneration Act HGRA.
- Midland Expressway Ltd v Carillion Construction Ltd & Others.
- Private finance initiative.
Featured articles and news
A UK training and membership provider for mould remediation professionals.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
Independent NSI and BAFE study exploring how organisations are changing the way they buy fire safety services.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.
Setting Expectations on Competence Management
Industry Competence Committee.
New Scottish and Welsh governments
CIOB stresses importance of construction after new parliament elections.
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.